NOIDA vs Rajveer Singh (2026): Supreme Court Says Their Land Compensation Claim Missed a Deadline They Didn't Know Had Started
In 1977, the government acquired land in Ghaziabad and paid compensation to the landowners, who did not object. Forty-nine years, several rounds of litigation and one landmark Supreme Court ruling later, their descendants were told their claim for a higher payout was time-barred — because a three-month deadline they didn't know existed had already expired years before they filed. On 21 September 2026, the Supreme Court in New Okhla Industrial Development Authority & Anr. vs Rajveer Singh & Ors. (Civil Appeal arising out of SLP (C) No. 18801 of 2025) used the case to finally settle three decades of conflicting rulings on when the limitation clock under Section 28A of the Land Acquisition Act, 1894 actually starts ticking.
What Happened in This Case
An award for the acquired land was passed on 15 February 1977, and the predecessors of the respondents (Rajveer Singh & Ors.) accepted the compensation without seeking a reference under Section 18. Other landowners covered by the same notification did seek a reference, which was rejected by the Additional District Judge, Ghaziabad on 25 November 1981. Their First Appeal No. 458 of 1982 was finally disposed of by the High Court on 18 April 2022 — simply by following an earlier order in a connected First Appeal No. 593 of 1982, decided on 8 July 2019. Believing this gave them a fresh right, the respondents filed an application under Section 28A on 23 May 2022, within three months of the 2022 order. The Collector initially rejected it as not maintainable. A writ petition later forced expeditious consideration, and the matter eventually reached the High Court and then the Supreme Court.
What Section 28A Is Actually Meant to Do
Section 28A is a beneficial provision. It lets a landowner who never sought a reference under Section 18 still benefit from a higher compensation awarded to someone else's land under the very same acquisition notification — provided they apply within three months of that award, and only once. Without it, two neighbours whose land was acquired under the same notification could end up with wildly different compensation simply because one of them fought for a reference and the other didn't.
Three Decades of Conflicting Supreme Court Rulings
The question of when that three-month clock starts has divided Supreme Court benches for thirty years. In Union of India vs Pradeep Kumari (1995), a three-judge bench held that Section 28A could be invoked from any successive award of the Reference Court, not just the first one. A year later, in Jose Antonio Cruz vs Land Acquisition Collector (1996), another three-judge bench held that the ‘award of the court’ under Section 28A means only an award made by the Reference Court under Section 26 — not an appellate order — so limitation runs from the Reference Court's order, not from the High Court's decision in appeal. The Constitution Bench in Union of India vs Hansoli Devi (2002) noted this unresolved tension but left it open. In Banwari vs HSIIDC (2024), the Court carved out one exception: where a landowner's reference under Section 18 is rejected outright with no enhancement at all, and the first-ever enhancement only comes later in a First Appeal before the High Court, that First Appeal award can itself start the Section 28A clock.
Why the Respondents' Claim Failed
In this case, the real first enhancement in appeal had already happened on 8 July 2019, in the connected First Appeal No. 593 of 1982, concerning the same notification and the same village. That gave the respondents three months, until 7 October 2019, to file under Section 28A. Instead, they waited for their own First Appeal No. 458 of 1982 to be disposed of on 18 April 2022, which merely followed the 2019 order and enhanced nothing new. The Supreme Court held that this later order created no fresh cause of action: the Banwari exception applies only to the first enhancement after a rejected reference, and here that had already happened in 2019. The respondents' application, filed in May 2022, was therefore held to be roughly two-and-a-half years too late — even though it was filed well within three months of the order they thought mattered.
The Six Conditions for Section 28A, Reaffirmed
An award has been made by the Reference Court under Part III after Section 28A came into force.
That award grants compensation in excess of what the Collector awarded under Section 11.
The applicant is interested in other land covered by the same Section 4(1) notification as that award.
The applicant did not themselves apply for a reference under Section 18.
The application under Section 28A is moved within three months of the award relied on.
Only one application can ever be moved under Section 28A by a given applicant.
What This Means for Lawyers and Law Students
The judgment also disapproves of a 2026 two-judge bench decision, Andanayya vs Deputy Chief Engineer, which had allowed a second Section 28A application after a High Court appellate enhancement on a ‘doctrine of merger’ theory — the Court called this directly in conflict with two three-judge bench precedents. For anyone practising land acquisition law, the lesson is procedural and unforgiving: a landowner who has not filed their own reference under Section 18 must track every award passed on a reference relating to the same notification — not just the appeal they happen to be following — because the three-month Section 28A clock can start and expire long before the case they're watching is even decided. Getting this wrong, as this case shows, can cost decades of litigation and the compensation itself.
Cases like this show why precise tracking of limitation periods, cross-referencing multiple rounds of litigation and correct application drafting matter so much in land acquisition and civil practice. ILW's Advanced Legal Drafting 6.0 course trains law students and young lawyers in exactly this kind of procedural and drafting rigour.
For more Supreme Court case breakdowns like this one, join ILW's WhatsApp channel for regular updates.
Frequently Asked Questions
What is Section 28A of the Land Acquisition Act, 1894?
It is a beneficial provision that lets a landowner who did not seek a reference under Section 18 still claim the higher compensation awarded to another landowner's land under the same acquisition notification, by applying to the Collector within three months of that award.
When does the limitation period under Section 28A begin?
As a rule, it begins from the date of the award passed by the Reference Court under Section 26 — not from an order passed later in appeal by the High Court. The only exception is where the reference itself was rejected outright with no enhancement, in which case the first enhancement granted later in a First Appeal can start the clock.
Can a person who never filed a reference under Section 18 still claim under Section 28A?
Yes. That is exactly the purpose of Section 28A — it lets such a person ride on the enhanced compensation obtained by another landowner covered by the same notification, provided they act within three months and have not filed a reference of their own.
What did the Supreme Court decide in NOIDA vs Rajveer Singh (2026)?
The Court held that the respondents' Section 28A application was barred by limitation. The real first enhancement in appeal had occurred in 2019, and a later 2022 order that merely followed it did not create a fresh cause of action, so the three-month period had already expired well before the application was filed.
Can more than one application be filed under Section 28A?
No. The Supreme Court reaffirmed that only one application can be moved under Section 28A by a given applicant for redetermination of compensation.
Read the Full Judgment
Supreme Court judgment dated 21 September 2026: New Okhla Industrial Development Authority & Anr. vs Rajveer Singh & Ors. — Google Drive copy of the judgment | Download PDF
Keywords: Section 28A Land Acquisition Act, NOIDA vs Rajveer Singh, Land Acquisition Act 1894, limitation period land compensation, Section 28A limitation Supreme Court, redetermination of compensation, Pradeep Kumari case, land acquisition compensation India, Banwari vs HSIIDC, Jose Antonio Cruz case





Comments