The Railways Wrote “No Interest” Into the Contract. The Tribunal Renamed It “Compensation.” The Supreme Court Wasn’t Fooled (Union of India v. L&T, 2026 INSC 203)
Updated: Sep 22
Every argument about interest in arbitration comes down to one question: who controls the price of delay, the parties who signed the contract or the tribunal that decides their dispute? On 27 February 2026, the Supreme Court gave a two-part answer in Union of India v. Larsen & Toubro Limited (2026 INSC 203), and it moved real money. The best way to understand it is to follow the rupee, stop by stop, from a Railways workshop contract to the final ledger.
The Ruling in Numbers
Case: Union of India & Ors. v. Larsen & Tubro Limited (L&T), appeal arising out of SLP (Civil) No. 14989 of 2023 (2026 INSC 203).
Bench: Justice Sanjay Karol and Justice Vipul M. Pancholi. The judgment text opens with Justice Pancholi’s name.
Decided on: 27 February 2026, New Delhi.
Counsel: Ms. Aishwarya Bhati, Additional Solicitor General, for the Union of India and Railways, and Ms. Meenakshi Arora, Senior Advocate, for L&T.
Pre-award and pendente lite interest: struck down for Claim Nos. 1, 3 and 6.
Post-award interest: upheld, but the rate is cut from 12% to 8% per annum from the date of award till realisation.
Outcome: appeal partly allowed.
Stop One: A Rs. 93 Crore Workshop and a 40-Month Delay
The story starts with an Agreement dated 27.01.2011 (No. CME/NCR/JHSW/MOD/2010, Turnkey) between the Union of India and North Central Railway Administration on one side and L&T on the other. The job was the modernisation of the Jhansi Workshop of North Central Railways, at a negotiated value of Rs. 93,08,07,696.
The original completion date was 18.07.2012, an 18-month timeline. The Railways extended it ten times, until 30.11.2015, which the judgment records as a total delay of 40 months beyond the original deadline. Disputes over execution and outstanding payments followed. The General Conditions of Contract (GCC) carried the arbitration agreement in Clause 64.
Stop Two: Eight Claims and a Counter-Claim
L&T applied on 04.09.2017 for the appointment of an Arbitral Tribunal. Under Clause 64(3), a three-member tribunal was constituted and entered upon the reference on 10.01.2018. L&T’s revised claims were:
Claim 1: financing charges for inordinate delay in release of payments against running account bills.
Claim 2: cost of variations in the foreign exchange currency component beyond the original contract period.
Claim 3: non-payment of the Price Variation Component (PVC) and interest.
Claim 4: indirect costs during the extended stay in the project.
Claim 5: refund of the amount recovered as token liquidated damages.
Claim 6: payment due against the final bill and variation for additional works, with interest.
Claim 7: interest on the claim amount at 18%.
Claim 8: costs of arbitration.
The Railways’ counter-claim: losses due to late commissioning of the CNC Portal Wheel Lathe.
Stop Three: The Award, Line by Line
On 25.12.2018 the Tribunal delivered its award. Here is the ledger as the judgment reproduces it:
Claim 1: claimed Rs. 2,26,25,891, awarded Rs. 1,77,78,727.
Claim 2: claimed Rs. 2,21,00,586, awarded nil.
Claim 3: claimed Rs. 98,44,886 (as printed), awarded Rs. 1,70,18,577.
Claim 4: claimed Rs. 5,70,04,383, awarded nil.
Claim 5: claimed Rs. 2,00,000, awarded nil.
Claim 6: claimed Rs. 1,67,51,576, awarded Rs. 2,28,70,261.
Claim 7 (interest at 18%): claimed Rs. 10,27,41,682, awarded nil.
Claim 8 (costs): claimed Rs. 29,88,947, awarded Rs. 7,90,032.
Total awarded: Rs. 5,84,57,597. Against this, the Railways’ counter-claim of Rs. 8,95,25,520 was allowed to the extent of Rs. 31,00,000.
Net payable to L&T: Rs. 5,53,57,597 within 60 days, failing which the sum would carry post-award interest at 12% per annum from the date of award.
Notice something odd. The Tribunal refused Claim 7, the direct claim for interest, because interest was not admissible under Section 31(7)(a) of the Act read with Clause 64(5) of the GCC and Clause 7.35 of the Special Conditions. Yet three other heads, Claims 1, 3 and 6, carried financing charges and interest-linked amounts. The Tribunal justified them as compensation, remarking that it would be a travesty of justice not to pay it when the principal sum was admitted by the Railways but simply not paid. That tension is the heart of the case.
Stop Four: Two Courts Let the Award Stand
The Union of India challenged the award under Section 34 before the Commercial Court, Jhansi, arguing chiefly that the interest and compensation violated Clauses 16(3) and 64(5) of the GCC. It also attacked the lump sum legal fees. The Commercial Court dismissed the application on 15.09.2022, stressing that the scope of interference under Section 34 is limited.
The Allahabad High Court, in an appeal under Section 37 (Appeal No. 433 of 2023), agreed on 25.05.2023. Its reading was that Clause 16(3) related only to earnest money and security deposits, and that Clause 64(5) merely barred pendente lite interest, which the Tribunal had interpreted correctly. The Railways then came to the Supreme Court.
Stop Five: The Two Sides of the Argument
The Railways argued:
Clause 16(3) bars interest on the earnest money, on the security deposit and also on “the amounts payable to the Contractor under the Contract”, so it is an absolute bar covering delayed payments of the final bill, PVC amounts and withheld dues.
Calling the interest “compensation” is an attempt to get around the bar, and this was rejected in Sree Kamatchi Amman Constructions v. Railway Administration (2010) 8 SCC 767.
The arbitrator is a creature of the contract. Union of India v. Bright Power Projects (India) (P) Ltd. (2015) 9 SCC 695 (three judges) and Union of India v. Manraj Enterprises (2022) 2 SCC 331 hold that where interest is barred, the arbitrator cannot award it under any name.
Section 73 of the Contract Act applies “unless the contract provides otherwise”, and here the contract does.
R.P. Garg v. Chief General Manager, Telecom Department (2024) applies only where the contract does not prohibit interest, and Section 31(7)(b) is expressly subject to Section 31(7)(a).
L&T replied:
The findings were concurrent, given by both the Commercial Court and the High Court.
Clause 16(3) must be read by the rule of ejusdem generis, so “amounts payable to the Contractor” means only sums deposited with the other party, as held in Raveechee and Company v. Union of India (2018) 7 SCC 664.
Clause 64(5) covers only disputed sums adjudicated by the award, so admitted sums such as Claims 3 and 6 are not hit and should carry full interest.
Post-award interest flows from Section 31(7)(b), as R.P. Garg holds, and the precedents relied on by the Railways do not apply.
Stop Six: The Red Line on Pre-Award and Pendente Lite Interest
The Court framed three issues: whether the Tribunal could award pre-award or pendente lite interest by way of compensation given Clauses 16(3) and 64(5); whether it could award post-award interest; and whether the courts below erred in dealing with both. On the first, its reasoning ran in five steps.
The statute defers to the contract. Section 28(3) requires the Tribunal to take into account the terms of the contract, and Section 31(7)(a) opens with “unless otherwise agreed by the parties”. The Court said the statutory scheme itself subordinates the arbitrator’s discretion on interest to the contract.
Ejusdem generis does not rescue Clause 16(3). The rule applies only where general words follow a specific class forming a genus. The expression “amounts payable to the Contractor under the Contract” is independent, distinct and of wide amplitude, and it cannot be read down. The Court relied on Manraj Enterprises, which reasoned that the word “or”, not “and”, separates the categories.
The precedent line points one way. The Court reproduced Bright Power Projects and Sree Kamatchi Amman Constructions, and explained that Ambica Construction (2017) and Raveechee (2018), on which L&T leaned, were decided under the Arbitration Act, 1940, whereas this dispute falls under the 1996 Act, which contains a specific provision on party agreement.
A new label does not change the substance. The Tribunal could not award pre-award or pendente lite interest even in the form of compensation, in view of Clause 16(3) read with Clause 64(5).
The Tribunal had itself acknowledged the bar. By rejecting Claim 7 on the strength of Section 31(7)(a) and Clause 64(5), the Tribunal accepted the prohibition, so allowing the same thing under Claims 1, 3 and 6 was a serious error.
Why the courts below were overruled: awarding pendente lite interest against an express contractual bar is the kind of error that attracts interference even within the limited scope of Sections 34 and 37.
Stop Seven: Where the Money Kept Flowing, Post-Award Interest
If pre-award interest was the Railways’ victory, post-award interest was L&T’s. The Court explained that Section 31(7)(b) exists for two reasons: to compensate the successful party for delayed realisation and to push the award-debtor to comply promptly. It relied on R.P. Garg, which distinguishes interest before the award, governed by the agreement under Section 31(7)(a), from interest after the award, governed by Section 31(7)(b).
Clause 64(5) bars interest only “till the date on which the award is made”. It says nothing about the period after.
Nothing in the GCC expressly bars post-award interest, so the statutory mandate prevails.
The Railways’ argument that a bar on pre-award interest overrides Section 31(7)(b) was rejected. Pre-award and post-award interest operate in distinct fields, and any exclusion of post-award interest must be explicit and unambiguous.
The Tribunal’s direction was also conditional. The 12% would apply only if the Railways did not pay within 60 days, so it operated as a deterrent against delay, not an automatic or punitive charge.
Stop Eight: The Discount From 12% to 8%
Having upheld the principle, the Court cut the rate. It found 12% per annum on the higher side because the Tribunal gave no reasons for choosing it, and, in the light of the contemporary economic scenario, such a rate would be an excessive burden and would not serve just compensation.
For the power to do so, it turned to Gayatri Balasamy v. M/s. ISG Novasoft Technologies Limited (2025) 7 SCC 1, paragraphs 74 to 78. As the Court read it, courts retain the power to modify post-award interest under Section 31(7)(b) where the facts justify it, because such interest is future-oriented and modification avoids setting aside a whole award merely over interest. The rate was accordingly reduced to 8% per annum from the date of award till realisation.
The Final Ledger: Before and After
Pre-award and pendente lite interest, or amounts in the nature of interest, under Claims 1, 3 and 6: allowed by the Tribunal and both courts, now set aside.
Post-award interest: allowed at 12%, now upheld in principle at 8% per annum from the date of award till realisation.
Set aside: the Allahabad High Court judgment of 25.05.2023, the Commercial Court order of 15.09.2022 and the Arbitral Award of 25.12.2018, to the extent of the pre-award and pendente lite interest.
Disposal: the appeal is partly allowed and pending applications stand disposed of.
A Note on the Record Before You Cite This Judgment
Authorship: the printed header lists Justice Sanjay Karol as author, but the judgment text opens with Justice Vipul M. Pancholi’s name. Check the certified copy before attributing it to one Judge.
Unquantified impact: Claims 1, 3 and 6 together carry Rs. 5,76,67,565 in the award, but the judgment does not say how much of that is interest or interest-like, so the revised payable amount is not computed.
Post-award interest wording: the R.P. Garg passage quoted in paragraph 48 says clause (b) is not subject to party autonomy, while paragraph 56 says post-award interest flows unless parties unequivocally exclude it. Read the two together, and if you are drafting, treat explicit and unambiguous exclusion as the only safe route.
Clause numbering: the Manraj Enterprises passage in the judgment refers to Clause 16(2), and this contract’s clause is 16(3). The wording is the same, but do not mix the numbers when quoting.
Scope: the Section 34 challenge also attacked the lump sum legal fees, but the Supreme Court’s three issues deal only with interest.
What Lawyers and Law Students Should Take From This Judgment
Read the interest clause word by word. One conjunction, “or” instead of “and”, decided whether ejusdem generis applied. Check the exact wording before you argue for or against a narrow reading.
A renamed claim is still the same claim. If interest is barred, describing it as compensation, financing charges or damages for delay will not survive scrutiny if the substance is interest.
Check which Act the authority was decided under. Raveechee and Ambica lost their force here because they were decided under the 1940 Act.
Section 34 and 37 are narrow, not shut. Awarding relief against an express contractual bar is a ground for interference, even when two courts have already upheld the award.
Draft post-award interest deliberately. A bar on pre-award interest does not touch Section 31(7)(b). If parties want post-award interest excluded, they must say so in explicit and unambiguous words.
Reason the rate. A tribunal that fixes a post-award rate without reasons invites a court to modify it, as happened here.
Where the Money Is Made or Lost: In the Contract
Look at how this case was decided. A few lines in a General Conditions of Contract, a comma, a conjunction and the word “till”, moved crores of rupees and produced years of litigation across four forums. The lawyers who make that kind of difference are usually the ones who drafted the clause or argued its meaning.
Into Legal World’s Advanced Legal Drafting 6.0 course trains law students and lawyers to draft and vet contract clauses, including payment, interest and dispute resolution terms, with live classes, recorded lectures, downloadable drafts, 1:1 mentorship and placement support. To go from drafting the clause to arguing it before a tribunal or court, add the Advanced Certificate Course in Arbitration & Dispute Resolution. ILW has trained more than 1,05,000 legal professionals since 2018, and you can explore every certificate programme at intolegalworld.com.
Frequently Asked Questions
Can an arbitral tribunal award pre-award or pendente lite interest if the contract bars interest?
No. In Union of India v. Larsen & Toubro Limited (2026 INSC 203), the Supreme Court held that Section 31(7)(a) of the Arbitration and Conciliation Act, 1996 begins with “unless otherwise agreed by the parties”, so where the contract bars interest the tribunal cannot award pre-award or pendente lite interest. Clause 16(3) of the GCC, read with Clause 64(5), barred it here, and the Tribunal’s award of such interest under Claims 1, 3 and 6 was set aside.
Can a tribunal award compensation in place of interest that the contract prohibits?
Not if the compensation is in substance interest. The Supreme Court held that the tribunal could not award pre-award or pendente lite interest even in the form of compensation, in view of the express contractual bar. The Tribunal itself had rejected the direct claim for interest under Section 31(7)(a) and Clause 64(5), which made awarding interest-like amounts under other heads a serious error.
Is post-award interest payable when the contract bars interest on amounts payable to the contractor?
Yes, unless the contract explicitly excludes it. The Court held that post-award interest under Section 31(7)(b) operates in a distinct field from pre-award interest, that Clause 64(5) barred interest only till the date of the award, and that any exclusion of post-award interest must be explicit and unambiguous. Nothing in the GCC barred it, so post-award interest was upheld.
Can a court reduce the rate of post-award interest fixed by an arbitral tribunal?
Yes, where the facts justify it. Relying on Gayatri Balasamy v. ISG Novasoft Technologies Limited (2025) 7 SCC 1, the Supreme Court said courts retain the power to modify post-award interest under Section 31(7)(b). It found the Tribunal’s 12% per annum too high because no reasons were given and reduced it to 8% per annum from the date of award till realisation.
What are the citation, Bench and case numbers for this judgment?
The judgment is reported as 2026 INSC 203 and was decided on 27 February 2026 in New Delhi by a Bench of Justice Sanjay Karol and Justice Vipul M. Pancholi. It arises from SLP (Civil) No. 14989 of 2023 and challenges the Allahabad High Court’s judgment of 25.05.2023 in Appeal No. 433 of 2023 under Section 37, which upheld the Commercial Court, Jhansi’s order of 15.09.2022 and the Arbitral Award of 25.12.2018 in favour of Larsen & Toubro Limited against the Union of India and North Central Railway.
Read the full judgment: Download PDF | View on Google Drive
Stay updated: Join ILW’s WhatsApp Channel for daily case analyses, legal job alerts and course updates.
Keywords: 2026 INSC 203, Union of India v. Larsen & Toubro, L&T v. Railways arbitration, pre-award interest arbitration, pendente lite interest arbitration, Section 31(7)(a) Arbitration and Conciliation Act, Section 31(7)(b) post-award interest, contractual bar on interest, ejusdem generis arbitration clause, Clause 16(3) GCC railway contract, Clause 64(5) GCC interest, Section 34 setting aside arbitral award, Section 37 arbitration appeal, Bright Power Projects, Manraj Enterprises, Sree Kamatchi Amman Constructions, R.P. Garg v. Chief General Manager Telecom, Gayatri Balasamy v. ISG Novasoft, modification of post-award interest, Supreme Court arbitration judgment 2026, railway contract arbitration India, Arbitration and Dispute Resolution course, Advanced Legal Drafting course.





Comments